Bridge Over Interstate 229 - Structure work North of 26th Street



Project Summary:

This project includes bridge rehab work on multiple bridges, the bridges included in the project are: 
- Big Sioux River Bridge
- BNSF Railroad Bridge
- Bridge over Interstate 229 (26th Street). Including an epoxy deck seal.

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text "I229Exit5" to 605-566-4041


Project Timeline:

June 2024 - Spring 2025

Project Updates:

Dec. 20, 2024:

Oct. 15, 2024 – Nov. 15, 2024, Completed Work
:
The contractor completed crash wall struts on the 26th Street bridge in the I-229 north shoulder. They alsoinstalled guardrail on the I-229 bridges north of 26thStreet. 

Anticipated work Nov. 15, 2024 – Dec. 15, 2024: The remaining work will be completed in Spring 2025. At that point the contractor plans to finish the epoxy chip seal of the 26th Street bridge deck and I-229 southbound bridge over railroad and Southeastern Avenue. 


Project Photos:


Project Contract Amount:

$1.9 Million

Project Contacts:

Contractor:
BX Civil & Construction 
605-428-5483

 
SDDOT: 
Bridger Kraye
605-940-1879