S.D. Highway 25 - North of De Smet


Project Summary:

Phase One (April 12, 2023 - June 2024): This project consists of grading, including the removal of existing surfacing to be recycled for the new base, new ditches and a wider roadway. Multiple box culverts will be replaced, all new pipe, and blotter surface will be completed.

Phase Two (June 2024 - October 2024): This project consists of asphalt concrete surfacing with increased shoulder widths. 

 

Project Photos:

{!SLIDESHOW=39}
 


Project Contract Amount:

Phase One: $18.3 Million

Phase Two: $9 Million


Project Contacts:

Contractor: 

Phase One:
Midland Contracting, Inc.
605-352-2400

Phase Two: 
Asphalt Paving & Materials Company - Huron
Nathan Tomczak
605-352-3502

SDDOT:
Huron Area Engineer
Brad Letcher  
605-353-7140


STATEWIDE CONSTRUCTION PROJECTS PAGE



PCN 04XC/064U & 064X/064V